onsdag den 29. september 2010

Concept art: Bears

I updated and added something on these bears. The evil bear got more details and a new black t-shirt. The another, the good bear got fur and vest, but I'm not happy with the vest yet. It will probably be new updates soon.

tirsdag den 28. september 2010

Report from meeting Tuesday 28/009/2010

We had a meeting with our supervisor, Bård, where we talked about our plans and showed him what we have done so far.

Bård told us to focus on creating concept art, storyboard, and testing out all the effects we want to use in our film; fur, lighting, particles. He also told us that our film has to be at least 5 minutes. Considering the size of this project and the group, so that everyone has to contribute.


We have been working on the project management document, progress plan and milestone plan. The milestone plan for the August-December period has been changed.